The exterior of all buildings have been painted. Synthetic turf has been installed on the football field. The insulation of heating pipes and the replacement of asphalt pathways is complete. The demolition of the breezeway between the 200 Building and the 300 Building is also complete. The windows at the snack bar have been replaced and new roll-up grills will be installed over the new windows for additional security.
Scheduled for 2005 – There will be new lights installed at the football field. There are landscape upgrades for the first and second Quad scheduled. Playfield upgrades to the baseball and softball fields are planned as well as the re-surfacing of the tennis courts. There is also a possibility that new entry gates will be installed at the entry to the upper site to limit vehicle trespass at off-hours.